Community Pressure Brings Progress, But Farming Concerns Remain
ElectraNet has chosen its preferred corridor for the Northern Transmission Project, bringing welcome relief to farming communities around Riverton and Saddleworth, but leaving other landholders with plenty of unanswered questions.
Corridor 5, between Bundey and Freeling, has been selected for further investigations into the proposed high-voltage transmission line.
The decision follows months of community opposition to four earlier routes through some of South Australia’s most productive cropping country.
Northern Transmission Project – How Did We Get Here?

The Northern Transmission Project (NTx) aims to strengthen South Australia’s electricity network between the Upper Spencer Gulf, Mid North and Adelaide’s northern suburbs.
The original four corridors sparked considerable backlash from farmers and residents around Eudunda, Manoora, Riverton, Saddleworth and surrounding districts.
Concerns ranged from losing productive farmland to restrictions on machinery, aerial spraying, biosecurity and fire safety.
Following months of community pressure, ElectraNet agreed to investigate a fifth corridor further east.
That option has now become the preferred corridor, although ElectraNet stresses the final route has not been determined.
Relief For Clare And Gilbert Valleys
Clare & Gilbert Valleys Council Mayor Allan Aughey OAM welcomed the decision, saying community feedback had helped influence the outcome.
“We are very pleased that ElectraNet has selected a preferred corridor that moves investigations away from the earlier options around Riverton and Saddleworth. This is welcome news for residents and farming families who have faced considerable uncertainty about the potential impacts on their properties, livelihoods and communities. It is encouraging to see community feedback and local knowledge helping to shape a decision of this significance,” Clare & Gilbert Valleys Mayor Allan Aughey OAM said.
He also acknowledged that landholders within the preferred corridor now face uncertainty of their own.
“We also recognise that landholders within the preferred corridor will have concerns of their own and encourage ElectraNet to continue working closely and respectfully with everyone who may be affected.”
GPSA Says Questions Remain Unanswered
Grain Producers SA (GPSA) says selecting a preferred corridor doesn’t resolve the concerns farmers have repeatedly raised.
Chief Executive Officer Brad Perry said growers were still waiting for clear information about how the infrastructure would affect their businesses.
“Today’s announcement narrows the area under consideration, but our fundamental concerns remain. Growers need clear answers and commitments they can rely on for future planning for their businesses.”
GPSA wants greater clarity around machinery access, aerial spraying, precision agriculture, biosecurity, soil protection and ongoing maintenance.
Compensation is another major sticking point, with GPSA calling for South Australian growers to receive arrangements comparable to those offered interstate, including indexed annual payments.
“GPSA will not consider support for any proposed route while affected South Australian grain producers face inferior compensation arrangements compared to their interstate counterparts,” Mr Perry said.
“South Australia needs reliable and affordable electricity, and it also needs viable farms and productive land. Both must be properly valued.”
What Happens Next?
ElectraNet will continue investigating Corridor 5, subject to the project’s cost-benefit assessment. The announcement does not constitute project approval or confirmation of the final transmission line route.
For some Mid North communities, the decision is welcome news after months of uncertainty. For others, the conversation is far from over.
More information is available at ntxproject.com.au.